Assessment Year | 1996 |
---|---|
Principal Product | Iron Castings |
NAICS |
n/a
|
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
90,000
ft2
|
Annual Production | 40,000
ton
|
Production Hrs. Annual | 4,200
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $817,975 | 16,189,039 |
kWh
|
$0.051 |
Electricity Demand | $259,320 | 38,388 |
kW-mo/yr
|
$6.76 |
Natural Gas | $126,229 | 116,180 |
MMBtu
|
$1.09 |
Other Energy | $1,483,034 | 175,702 |
MMBtu
|
$8.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $91,308 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $46,046 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $4,034 | $4,746 |
$3,226
63,892
kWh
|
$808
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $1,906 | $400 |
$1,205
23,740
kWh
|
$701
-
kW-mo/yr
|
- | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $37,610 | $85,150 | - | - |
$37,610
-
MMBtu
|
|
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,708 | $2,145 |
$4,854
95,838
kWh
|
$1,854
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,012 | - |
$1,630
27,843
kWh
|
$382
-
kW-mo/yr
|
- | |
06 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $1,865 | $6,500 |
$1,356
26,964
kWh
|
$509
-
kW-mo/yr
|
- | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $5,746 | $12,550 | - | - |
$5,746
-
MMBtu
|
|
08 | 2.2515: Use optimum thickness insulation | $26,973 | $3,335 |
$19,191
379,543
kWh
|
$7,782
-
kW-mo/yr
|
- | |
09 | 2.2511: Insulate bare equipment | $4,454 | $3,975 | - | - |
$4,454
-
MMBtu
|
|
TOTAL RECOMMENDED | $91,308 | $118,801 |
$31,462
617,820
kWh
|
$12,036
-
kW-mo/yr
|
$47,810
-
MMBtu
|
||
TOTAL IMPLEMENTED | $46,046 | $20,701 |
$30,257
594,080
kWh
|
$11,335
-
kW-mo/yr
|
$4,454
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs