Assessment Year | 1995 |
---|---|
Principal Product | Anodized Aluminum |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | less than $500 k |
# of Employees | 8 |
Plant Area |
12,000
ft2
|
Annual Production | 454,920
lb
|
Production Hrs. Annual | 2,346
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $16,033 | 117,819 |
kWh
|
$0.14 |
Natural Gas | $46,284 | 7,233 |
MMBtu
|
$6.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,585 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,149 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $510 | - |
$510
5,275
kWh
|
- | - | - | |
02 | 2.4314: Use synthetic lubricant | $79 | $169 |
$79
879
kWh
|
- | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,389 | $1,123 | - |
$3,389
-
MMBtu
|
- | - | |
04 | 2.2514: Cover open tanks | $98 | $77 |
$98
879
kWh
|
- | - | - | |
05 | 3.5314: Use in-process recycling whenever possible | $462 | $250 | - | - | - | $462 | |
06 | 3.1222: Reduce water use with counter current rinsing | $4,047 | $933 | - | - |
$4,047
-
Tgal
|
- | |
TOTAL RECOMMENDED | $8,585 | $2,552 |
$687
7,033
kWh
|
$3,389
-
MMBtu
|
$4,047
-
Tgal
|
$462 | ||
TOTAL IMPLEMENTED | $1,149 | $496 |
$687
7,033
kWh
|
- | - | $462 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs