ITAC Assessment: SF0065
ITAC logo
ITAC Assessment: SF0065
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Wood Framing
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 80,000
ft2
Annual Production 20,000
thousand feet
Production Hrs. Annual 4,160
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $321,541 2,525,791
kWh
Natural Gas $289 15
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,754 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,027

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $1,859 $2,279 $1,859
14,654
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,112 $5,208 $4,112
32,239
kWh
03 2.7134: Use photocell controls $791 $232 $791
6,155
kWh
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $999 $480 $999
7,913
kWh
05 2.6218: Turn off equipment when not in use $3,936 - $3,936
39,859
kWh
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $6,057 $2,010 $6,057
47,479
kWh
TOTAL RECOMMENDED $17,754 $10,209 $17,754
148,299
kWh
TOTAL IMPLEMENTED $13,027 $9,977 $13,027
102,285
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs