ITAC Assessment: SF0061
ITAC logo
ITAC Assessment: SF0061
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Plating Services
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $1
M
to 5
M
# of Employees 31
Plant Area 18,000
ft2
Annual Production 9,600
units
Production Hrs. Annual 2,574
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $29,233 230,363
kWh
Natural Gas $29,310 4,781
MMBtu
LPG $1,995 165
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,975 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,319

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings LPG Savings Water Disposal Savings Solid Waste (non-haz) Savings
01 2.7135: Install occupancy sensors $1,935 $360 $1,935
15,240
kWh
- - - -
02 2.4133: Use most efficient type of electric motors $129 $170 $129
1,172
kWh
- - - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $347 $1,570 $347
2,638
kWh
- - - -
04 2.2136: Install / repair insulation on steam lines $1,658 $2,208 - $1,658
-
MMBtu
- - -
05 2.1332: Convert combustion equipment to burn natural gas $733 $1,300 - $(-1,262.0)
-
MMBtu
$1,995
-
MMBtu
- -
06 2.2514: Cover open tanks $3,373 $1,560 - $3,373
-
MMBtu
- - -
07 3.4156: Use flow control valves on equipment to optimize water use $6,048 $2,955 - - - $6,048
-
Tgal
-
08 3.6114: Use precipitating agents in waste water treatment that produce the least quantity of waste $2,880 $25,300 - - - $2,880
-
Tgal
-
09 3.1244: Reduce solution drag-out to prevent solution loss $7,532 $1,288 - - - - $7,532
-
lb
10 3.4113: Treat and reuse rinse waters $10,340 $6,344 - - - $10,340
-
Tgal
-
TOTAL RECOMMENDED $34,975 $43,055 $2,411
19,050
kWh
$3,769
-
MMBtu
$1,995
-
MMBtu
$19,268
-
Tgal
$7,532
-
lb
TOTAL IMPLEMENTED $9,319 $3,666 $129
1,172
kWh
$1,658
-
MMBtu
- - $7,532
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings LPG Savings Water Disposal Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs