| Assessment Year | 1995 |
|---|---|
| Principal Product | Chocolate Bars and Chips |
| NAICS |
n/a
|
| SIC | 2066: Chocolate and Cocoa Products |
| Sales Range | $50 M to 100M |
| # of Employees | 200 |
| Plant Area |
700,000
ft2
|
| Annual Production | 25,000
ton
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $648,664 | 7,730,950 |
kWh
|
$0.084 |
| Natural Gas | $143,484 | 34,346 |
MMBtu
|
$4.18 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $570,892 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $193,474 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $3,715 | $3,548 |
$3,715
44,256
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,741 | $25,412 |
$9,741
116,061
kWh
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,509 | $2,695 |
$6,509
77,667
kWh
|
- | - | |
| 04 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $5,861 | $8,820 | - |
$5,861
-
MMBtu
|
- | |
| 05 | 2.3132: Recharge batteries on during off-peak demand periods | $699 | - |
$699
-
kWh
|
- | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $638 | $550 |
$638
7,620
kWh
|
- | - | |
| 07 | 2.3212: Optimize plant power factor | $1,778 | $3,588 |
$1,778
-
kWh
|
- | - | |
| 08 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $367,210 | $633,645 |
$550,402
6,600,528
kWh
|
$(-183,192.0)
-
MMBtu
|
- | |
| 09 | 2.6218: Turn off equipment when not in use | $2,569 | - |
$2,569
30,481
kWh
|
- | - | |
| 10 | 3.4111: Use closed cycle process to minimize waste water production | $172,172 | $282,160 | - | - |
$172,172
-
Tgal
|
|
| TOTAL RECOMMENDED | $570,892 | $960,418 |
$576,051
6,876,613
kWh
|
$(-177,331.0)
-
MMBtu
|
$172,172
-
Tgal
|
||
| TOTAL IMPLEMENTED | $193,474 | $314,365 |
$21,302
245,604
kWh
|
- |
$172,172
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs