ITAC Assessment: SF0055
ITAC logo
ITAC Assessment: SF0055
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Aluminum, Brass, and Zinc Die Castings
NAICS
n/a
SIC 3363: Aluminum Die-Castings
Sales Range $5
M
to 10
M
# of Employees 90
Plant Area 36,000
ft2
Annual Production 1,080,000
lb
Production Hrs. Annual 4,784
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $184,587 1,574,443
kWh
Natural Gas $129,349 28,677
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,860 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,428

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $1,011 $1,077 $1,011
8,499
kWh
-
02 2.7135: Install occupancy sensors $11,092 $7,040 $11,092
94,666
kWh
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $848 $526 $848
7,327
kWh
-
04 2.4314: Use synthetic lubricant $580 $732 $580
4,982
kWh
-
05 2.2123: Insulate feedwater tank $727 $140 - $727
-
MMBtu
06 2.2511: Insulate bare equipment $27,226 $4,400 - $27,226
-
MMBtu
07 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,376 $5,725 $1,646
14,068
kWh
$(-270.0)
-
MMBtu
TOTAL RECOMMENDED $42,860 $19,640 $15,177
129,542
kWh
$27,683
-
MMBtu
TOTAL IMPLEMENTED $1,428 $1,258 $1,428
12,309
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs