Assessment Year | 1994 |
---|---|
Principal Product | Roasted Coffee |
NAICS |
n/a
|
SIC | 2095: Roasted Coffee |
Sales Range | $100 M to 500M |
# of Employees | 400 |
Plant Area |
42,000
ft2
|
Annual Production | 40,000
ton
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $738,118 | 10,025,498 |
kWh
|
$0.074 |
Natural Gas | $236,907 | 82,915 |
MMBtu
|
$2.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,223 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $3,044 | $2,794 |
$3,044
41,325
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,403 | $9,820 |
$3,403
46,307
kWh
|
- | |
03 | 2.7135: Install occupancy sensors | $2,561 | $1,608 |
$2,561
34,877
kWh
|
- | |
04 | 2.4314: Use synthetic lubricant | $2,093 | - |
$2,093
28,429
kWh
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,020 | $250 |
$1,020
13,775
kWh
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,273 | $3,317 |
$4,273
58,030
kWh
|
- | |
07 | 2.4323: Use optimum size and capacity equipment | $3,427 | $2,665 | - |
$3,427
-
MMBtu
|
|
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,772 | $10,800 |
$7,772
105,510
kWh
|
- | |
09 | 2.1213: Direct warmest air to combustion intake | $11,302 | $3,350 | - |
$11,302
-
MMBtu
|
|
10 | 2.4323: Use optimum size and capacity equipment | $6,328 | $550 | - |
$6,328
-
MMBtu
|
|
TOTAL RECOMMENDED | $45,223 | $35,154 |
$24,166
328,253
kWh
|
$21,057
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs