Assessment Year | 1994 |
---|---|
Principal Product | Soft Drinks |
NAICS |
n/a
|
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
100,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $324,524 | 2,881,887 |
kWh
|
$0.11 |
Natural Gas | $49,395 | 8,883 |
MMBtu
|
$5.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,891 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,687 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $10,894 | $6,328 |
$10,894
96,717
kWh
|
- | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $10,436 | $25,500 |
$10,436
92,614
kWh
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,671 | $1,056 |
$6,671
59,496
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,370 | $6,101 |
$4,370
38,687
kWh
|
- | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,504 | $10,968 |
$4,504
40,152
kWh
|
$(-1,000.0)
-
MMBtu
|
|
06 | 2.3212: Optimize plant power factor | $2,101 | $2,758 |
$2,101
-
kWh
|
- | |
07 | 2.4314: Use synthetic lubricant | $486 | - |
$486
4,396
kWh
|
- | |
08 | 2.2136: Install / repair insulation on steam lines | $266 | $239 | - |
$266
-
MMBtu
|
|
09 | 2.6218: Turn off equipment when not in use | $163 | $600 |
$163
1,465
kWh
|
- | |
TOTAL RECOMMENDED | $38,891 | $53,550 |
$39,625
333,527
kWh
|
$(-734.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $22,687 | $13,724 |
$22,421
199,296
kWh
|
$266
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs