ITAC Assessment: SF0021
ITAC logo
ITAC Assessment: SF0021
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Microwave Components
NAICS
n/a
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area 24,000
ft2
Annual Production 500
pieces
Production Hrs. Annual 2,860
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,449 525,498
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,621 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,899

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7241: Install outside air damper / economizer on hvac unit $3,841 $13,000 $3,841
45,428
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,899 $5,951 $1,899
22,567
kWh
03 2.7135: Install occupancy sensors $1,234 $1,920 $1,234
14,654
kWh
04 2.4133: Use most efficient type of electric motors $342 $759 $342
4,103
kWh
05 2.6218: Turn off equipment when not in use $305 $1,840 $305
3,517
kWh
TOTAL RECOMMENDED $7,621 $23,470 $7,621
90,269
kWh
TOTAL IMPLEMENTED $1,899 $5,951 $1,899
22,567
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs