| Assessment Year | 2026 |
|---|---|
| Principal Product | Plastic Food Packaging |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 115 |
| Plant Area |
367,000
ft2
|
| Annual Production | 26,900,000
lb
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,661,670 | 17,346,000 |
kWh
|
$0.096 |
| Electricity Demand | $728,656 | 39,569 |
kW-mo/yr
|
$18.41 |
| Electricity Fees | $127,932 | - |
|
- |
| Natural Gas | $38,990 | 2,797 |
MMBtu
|
$13.94 |
| Other Gas | $2,726 | 1 |
MMBtu
|
$2,726.00 |
| TOTAL YEARLY COSTS | $2,559,974 | |||
| RECOMMENDED SAVINGS* | $931,717 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $13,962 | $40,000 |
$6,909
72,115
kWh
|
$7,053
-
kW-mo/yr
|
|
| 02 | 2.9114: Use solar heat to make electricty | $65,552 | $204,249 |
$36,139
377,230
kWh
|
$29,413
-
kW-mo/yr
|
|
| 03 | 2.3141: Use battery storage for demand control | $702,807 | $109,721 |
$(-80,443.3)
(-839,700)
kWh
|
$783,250
-
kW-mo/yr
|
|
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,901 | - |
$8,901
92,910
kWh
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $77,614 | $85,595 |
$56,817
593,078
kWh
|
$20,797
-
kW-mo/yr
|
|
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,575 | $27,600 |
$5,943
62,037
kWh
|
$1,631
-
kW-mo/yr
|
|
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,477 | $8,478 |
$9,005
93,996
kWh
|
$2,472
-
kW-mo/yr
|
|
| 08 | 2.3132: Recharge batteries on during off-peak demand periods | $5,832 | - | - |
$5,832
-
kW-mo/yr
|
|
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $125 | $508 |
$98
1,023
kWh
|
$27
-
kW-mo/yr
|
|
| 10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $37,873 | $48,210 |
$29,715
310,187
kWh
|
$8,158
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $931,717 | $524,362 |
$73,083
762,876
kWh
|
$858,634
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs