| Assessment Year | 2025 |
|---|---|
| Principal Product | CNC Machining |
| NAICS | 332710: Machine Shops |
| SIC | 3541: Machine Tools, Metal Cutting Types |
| Sales Range | $10 M to 50M |
| # of Employees | 97 |
| Plant Area |
65,000
ft2
|
| Annual Production | 500
units
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $23,814 | 326,894 |
kWh
|
$0.073 |
| Electricity Demand | $107,642 | 2,938 |
kW-mo/yr
|
$36.64 |
| TOTAL YEARLY COSTS | $131,456 | |||
| RECOMMENDED SAVINGS* | $72,191 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $156 | $424 |
$46
626
kWh
|
$110
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $947 | $3,752 |
$323
4,430
kWh
|
$624
-
kW-mo/yr
|
- | |
| 03 | 2.7233: Use properly designed and sized hvac equipment | $50,863 | $545,300 |
$36,681
503,167
kWh
|
$14,182
-
kW-mo/yr
|
- | |
| 04 | 2.4322: Use or replace with energy efficient substitutes | $2,339 | $25,895 |
$2,339
32,092
kWh
|
- | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,200 | $3,396 |
$560
7,681
kWh
|
$1,640
-
kW-mo/yr
|
- | |
| 06 | 2.1321: Replace fossil fuel equipment with electrical equipment | $14,843 | $23,800 |
$13,237
181,584
kWh
|
- | $1,605 | |
| 07 | 2.7135: Install occupancy sensors | $843 | $2,979 |
$323
4,430
kWh
|
$520
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $72,191 | $605,545 |
$53,509
734,011
kWh
|
$17,076
-
kW-mo/yr
|
$1,605 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs