Assessment Year | 2025 |
---|---|
Principal Product | Peptides |
NAICS | 032541: Pharmaceutical and Medicine Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
40,000
ft2
|
Annual Production | 2,646
lb
|
Production Hrs. Annual | 7,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $936,700 | 3,333,375 |
kWh
|
$0.28 |
Electricity Demand | $570,166 | 7,631 |
kW-mo/yr
|
$74.72 |
Electricity Fees | $(-389,795.0) | - |
|
- |
Natural Gas | $71,820 | 6,279 |
MMBtu
|
$11.44 |
TOTAL YEARLY COSTS | $1,188,891 | |||
RECOMMENDED SAVINGS* | $882,091 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $45,096 | $40,868 |
$21,210
75,480
kWh
|
$23,886
-
kW-mo/yr
|
- | |
02 | 2.3141: Use battery storage for demand control | $652,079 | $20,176 |
$(-52,280.8)
(-186,053)
kWh
|
$704,360
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,426 | $4,882 |
$9,005
32,046
kWh
|
$3,421
-
kW-mo/yr
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,038 | - |
$6,038
21,486
kWh
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $259 | $339 |
$178
632
kWh
|
$81
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $71,133 | $43,658 |
$48,860
173,880
kWh
|
$22,273
-
kW-mo/yr
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $39,892 | $6,700 |
$38,153
135,777
kWh
|
$1,739
-
kW-mo/yr
|
- | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,554 | $1,623 |
$3,815
13,577
kWh
|
$1,739
-
kW-mo/yr
|
- | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,761 | $2,117 |
$4,111
14,630
kWh
|
$2,650
-
kW-mo/yr
|
- | |
10 | 2.1221: Replace obsolete burners with more efficient ones | $4,061 | $10,319 | - | - |
$4,061
-
MMBtu
|
|
11 | 2.7234: Use heat pump for space conditioning | $33,554 | $29,800 |
$24,588
87,500
kWh
|
$8,966
-
kW-mo/yr
|
- | |
12 | 2.7135: Install occupancy sensors | $5,238 | $2,979 |
$3,795
13,507
kWh
|
$1,442
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $882,091 | $163,461 |
$107,472
382,463
kWh
|
$770,558
-
kW-mo/yr
|
$4,061
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs