ITAC Assessment: SD0666
ITAC logo
ITAC Assessment: SD0666
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Turbine Repair Services
NAICS 336412: Aircraft Engine and Engine Parts Manufacturing
SIC 7699: Repair Shops and Related Services, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 222
Plant Area 110,000
ft2
Annual Production 35
units
Production Hrs. Annual 4,375
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,952,519 6,487,804
kWh
Electricity Demand $1,164,278 15,253
kW-mo/yr
Electricity Fees $(-902,969.0) -
Natural Gas $30,053 2,339
MMBtu
TOTAL YEARLY COSTS $2,243,881
RECOMMENDED SAVINGS* $2,133,723 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.9114: Use solar heat to make electricty $963,108 $710,032 $464,368
1,542,750
kWh
$498,740
-
kW-mo/yr
-
02 2.3141: Use battery storage for demand control $966,126 $35,339 $(-79,809.0)
(-265,147)
kWh
$1,045,935
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $38,554 $8,532 $25,571
84,955
kWh
$12,983
-
kW-mo/yr
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $24,605 $7,436 $13,946
46,332
kWh
$10,659
-
kW-mo/yr
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,044 $8,592 $10,227
33,977
kWh
$7,817
-
kW-mo/yr
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $32,808 $9,897 $18,595
61,776
kWh
$14,213
-
kW-mo/yr
-
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $20,505 $5,269 $11,622
38,610
kWh
$8,883
-
kW-mo/yr
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $61,029 $46,078 $30,241
100,467
kWh
$30,674
-
kW-mo/yr
$114
09 2.1121: Use insulation in furnaces to facilitate heating / cooling $2,705 - $1,446
4,803
kWh
$1,259
-
kW-mo/yr
-
10 2.1121: Use insulation in furnaces to facilitate heating / cooling $5,431 $312 $2,905
9,652
kWh
$2,526
-
kW-mo/yr
-
11 2.1121: Use insulation in furnaces to facilitate heating / cooling $808 $104 $432
1,436
kWh
$376
-
kW-mo/yr
-
TOTAL RECOMMENDED $2,133,723 $831,591 $499,543
1,659,611
kWh
$1,634,066
-
kW-mo/yr
$114
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs