| Assessment Year | 2025 |
|---|---|
| Principal Product | Bioreactors |
| NAICS | 325414: Biological Product (except Diagnostic) Manufacturing |
| SIC | 2836: Biological Products, Except Diagnostic Substances |
| Sales Range | $100 M to 500M |
| # of Employees | 150 |
| Plant Area |
240,000
ft2
|
| Annual Production | 100,000
units
|
| Production Hrs. Annual | 5,633
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $879,531 | 2,906,458 |
kWh
|
$0.30 |
| Electricity Demand | $364,831 | 3,743 |
kW-mo/yr
|
$97.47 |
| Electricity Fees | $506,749 | - |
|
- |
| Natural Gas | $26,051 | 3,483 |
MMBtu
|
$7.48 |
| Other Gas | $32,640 | 1 |
MMBtu
|
$32,640.00 |
| TOTAL YEARLY COSTS | $1,809,802 | |||
| RECOMMENDED SAVINGS* | $978,814 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $614,791 | $395,505 |
$260,039
859,350
kWh
|
$354,752
-
kW-mo/yr
|
- | - | |
| 02 | 2.3141: Use battery storage for demand control | $203,574 | $5,892 |
$(-19,101.9)
(-63,126)
kWh
|
$222,676
-
kW-mo/yr
|
- | - | |
| 03 | 4.212: Adopt in-house material generation | $23,739 | $46,406 |
$(-8,901.0)
(-29,416)
kWh
|
- | - | $32,640 | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $58,983 | $101,750 |
$35,500
117,163
kWh
|
$6,892
-
kW-mo/yr
|
$16,591
-
MMBtu
|
- | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,342 | $2,233 |
$1,799
5,944
kWh
|
$1,543
-
kW-mo/yr
|
- | - | |
| 06 | 2.2622: Replace existing chiller with high efficiency model | $74,386 | $209,425 |
$74,386
245,821
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $978,814 | $761,211 |
$343,720
1,135,736
kWh
|
$585,863
-
kW-mo/yr
|
$16,591
-
MMBtu
|
$32,640 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs