ITAC Assessment: SD0645
ITAC logo
ITAC Assessment: SD0645
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Relay Panels, Switchgear and Enclosures
NAICS 335313: Switchgear and Switchboard Apparatus Manufacturing
SIC 3613: Switchgear and Switchboard Apparatus
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 88,000
ft2
Annual Production 1,224
units
Production Hrs. Annual 4,500
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $102,985 939,450
kWh
Electricity Demand $102,225 2,716
kW-mo/yr
Electricity Fees $11,070 -
TOTAL YEARLY COSTS $216,280
RECOMMENDED SAVINGS* $179,301 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $14,027 $20,044 $10,523
96,010
kWh
$3,504
-
kW-mo/yr
-
02 2.4133: Use most efficient type of electric motors $2,908 $5,515 $2,408
21,975
kWh
$500
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,560 $10,840 $2,906
26,513
kWh
$2,604
-
kW-mo/yr
$50
04 2.9114: Use solar heat to make electricty $55,997 $84,760 $23,476
214,200
kWh
$32,521
-
kW-mo/yr
-
05 2.3141: Use battery storage for demand control $48,532 - $(-2,959.2)
(-27,000)
kWh
$51,492
-
kW-mo/yr
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,170 $3,900 $1,628
14,850
kWh
$542
-
kW-mo/yr
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $520 $1,694 $208
1,898
kWh
$312
-
kW-mo/yr
-
08 2.3132: Recharge batteries on during off-peak demand periods $49,587 - - $49,587
-
kW-mo/yr
-
TOTAL RECOMMENDED $179,301 $126,753 $38,190
348,446
kWh
$141,061
-
kW-mo/yr
$50
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs