Assessment Year | 2023 |
---|---|
Principal Product | Antibodies, Cell Therapies |
NAICS | 325414: Biological Product (except Diagnostic) Manufacturing |
SIC | 2836: Biological Products, Except Diagnostic Substances |
Sales Range | $10 M to 50M |
# of Employees | 241 |
Plant Area |
115,000
ft2
|
Annual Production | 100,000
units
|
Production Hrs. Annual | 2,295
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $636,314 | 5,375,675 |
kWh
|
$0.12 |
Electricity Demand | $606,729 | 22,558 |
kW-mo/yr
|
$26.90 |
Electricity Fees | $(-4,214.0) | - |
|
- |
Natural Gas | $277,087 | 21,391 |
MMBtu
|
$12.95 |
TOTAL YEARLY COSTS | $1,515,916 | |||
RECOMMENDED SAVINGS* | $238,831 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $54,888 | $228,599 |
$22,087
201,705
kWh
|
$32,801
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,022 | $3,456 |
$464
3,442
kWh
|
$558
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,114 | $4,352 |
$1,470
13,421
kWh
|
$1,614
-
kW-mo/yr
|
$30 | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,642 | $5,868 |
$752
6,163
kWh
|
$890
-
kW-mo/yr
|
- | - | |
05 | 4.454: Modify startup/shutdown times | $90,974 | $2,500 |
$90,974
534,161
kWh
|
- | - | - | |
06 | 4.454: Modify startup/shutdown times | $87,191 | $2,500 | - | - | - |
$87,191
-
MMBtu
|
|
TOTAL RECOMMENDED | $238,831 | $247,275 |
$115,747
758,892
kWh
|
$35,863
-
kW-mo/yr
|
$30 |
$87,191
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs