| Assessment Year | 2022 |
|---|---|
| Principal Product | Sheet and Plate metal components |
| NAICS | 332322: Sheet Metal Work Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $5 M to 10M |
| # of Employees | 42 |
| Plant Area |
30,000
ft2
|
| Annual Production | 600,000
units
|
| Production Hrs. Annual | 3,825
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $67,112 | 106,955 |
kWh
|
$0.63 |
| Electricity Demand | $73,634 | 1,418 |
kW-mo/yr
|
$51.93 |
| Electricity Fees | $1,520 | - |
|
- |
| TOTAL YEARLY COSTS | $142,266 | |||
| RECOMMENDED SAVINGS* | $30,460 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $20,056 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,131 | $800 |
$8,967
14,290
kWh
|
$1,164
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,925 | $6,341 |
$7,860
12,525
kWh
|
$2,035
-
kW-mo/yr
|
$30 | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,372 | $8,800 |
$4,719
7,520
kWh
|
$1,653
-
kW-mo/yr
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,032 | - |
$4,032
6,426
kWh
|
- | - | |
| TOTAL RECOMMENDED | $30,460 | $15,941 |
$25,578
40,761
kWh
|
$4,852
-
kW-mo/yr
|
$30 | ||
| TOTAL IMPLEMENTED | $20,056 | $7,141 |
$16,827
26,815
kWh
|
$3,199
-
kW-mo/yr
|
$30 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs