Assessment Year | 2021 |
---|---|
Principal Product | Tempered Glass |
NAICS | 327215: Glass Product Manufacturing Made of Purchased Glass |
SIC | 3231: Glass Products, Made of Purchased Glass |
Sales Range | $10 M to 50M |
# of Employees | 43 |
Plant Area |
50,000
ft2
|
Annual Production | 425,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $152,481 | 1,166,280 |
kWh
|
$0.13 |
Electricity Demand | $65,798 | 4,618 |
kW-mo/yr
|
$14.25 |
Electricity Fees | $28,492 | - |
|
- |
TOTAL YEARLY COSTS | $246,771 | |||
RECOMMENDED SAVINGS* | $85,848 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,898 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7425: Clean or color roof to reduce solar load | $3,957 | $7,500 |
$3,236
24,760
kWh
|
$721
-
kW-mo/yr
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,346 | $568 |
$1,940
14,840
kWh
|
$406
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,898 | $2,500 |
$5,339
40,841
kWh
|
$559
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,430 | $10,300 |
$2,836
21,700
kWh
|
$594
-
kW-mo/yr
|
- | |
05 | 2.7124: Make a practice of turning off lights when not needed | $2,177 | - |
$1,534
11,737
kWh
|
$643
-
kW-mo/yr
|
- | |
06 | 3.1192: Reduce scrap production | $68,040 | $68,000 | - | - | $68,040 | |
TOTAL RECOMMENDED | $85,848 | $88,868 |
$14,885
113,878
kWh
|
$2,923
-
kW-mo/yr
|
$68,040 | ||
TOTAL IMPLEMENTED | $5,898 | $2,500 |
$5,339
40,841
kWh
|
$559
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs