| Assessment Year | 2021 |
|---|---|
| Principal Product | Metal Fabrication Parts |
| NAICS | 332322: Sheet Metal Work Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $1 M to 5M |
| # of Employees | 15 |
| Plant Area |
10,000
ft2
|
| Annual Production | 4,500
units
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $48,867 | 359,640 |
kWh
|
$0.14 |
| Electricity Demand | $31,584 | 2,135 |
kW-mo/yr
|
$14.79 |
| Electricity Fees | $1,805 | - |
|
- |
| TOTAL YEARLY COSTS | $82,256 | |||
| RECOMMENDED SAVINGS* | $82,887 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,080 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.1192: Reduce scrap production | $80,293 | $41,423 |
$4,293
31,591
kWh
|
- | $57,000 | $19,000 | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,211 | $2,620 |
$746
5,491
kWh
|
$441
-
kW-mo/yr
|
- | - | $24 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $869 | $450 |
$671
4,937
kWh
|
$198
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $514 | $520 |
$514
3,785
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $82,887 | $45,013 |
$6,224
45,804
kWh
|
$639
-
kW-mo/yr
|
$57,000 | $19,000 | $24 | ||
| TOTAL IMPLEMENTED | $2,080 | $3,070 |
$1,417
10,428
kWh
|
$639
-
kW-mo/yr
|
- | - | $24 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs