| Assessment Year | 2019 |
|---|---|
| Principal Product | Beer |
| NAICS | 312120: Breweries |
| SIC | 2082: Malt Beverages |
| Sales Range | $100 M to 500M |
| # of Employees | 130 |
| Plant Area |
115,100
ft2
|
| Annual Production | 285,000
bbl
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $602,591 | 5,428,387 |
kWh
|
$0.11 |
| Electricity Demand | $562,070 | 13,773 |
kW-mo/yr
|
$40.81 |
| Electricity Fees | $(-15,519.0) | - |
|
- |
| Natural Gas | $108,934 | 42,167 |
MMBtu
|
$2.58 |
| TOTAL YEARLY COSTS | $1,258,076 | |||
| RECOMMENDED SAVINGS* | $32,399 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,655 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,052 | $8,453 |
$5,582
50,282
kWh
|
$3,290
-
kW-mo/yr
|
- | $180 | |
| 02 | 2.2441: Preheat boiler makeup water with waste process heat | $11,628 | $12,000 | - | - |
$11,628
-
MMBtu
|
- | |
| 03 | 2.6218: Turn off equipment when not in use | $2,603 | $200 |
$2,603
23,447
kWh
|
- | - | - | |
| 04 | 2.7134: Use photocell controls | $2,188 | $3,520 |
$2,188
19,715
kWh
|
- | - | - | |
| 05 | 2.4323: Use optimum size and capacity equipment | $6,928 | $14,000 |
$2,030
18,203
kWh
|
$4,898
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $32,399 | $38,173 |
$12,403
111,647
kWh
|
$8,188
-
kW-mo/yr
|
$11,628
-
MMBtu
|
$180 | ||
| TOTAL IMPLEMENTED | $11,655 | $8,653 |
$8,185
73,729
kWh
|
$3,290
-
kW-mo/yr
|
- | $180 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs