ITAC Assessment: SD0575
ITAC logo
ITAC Assessment: SD0575
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product custom molded rubber
NAICS 326299: All Other Rubber Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 40
Plant Area 35,000
ft2
Annual Production 300
units
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $99,747 1,324,443
kWh
Electricity Demand $72,537 3,837
kW-mo/yr
Electricity Fees $16,017 -
TOTAL YEARLY COSTS $188,301
RECOMMENDED SAVINGS* $11,286 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,951

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,276 $7,083 $3,394
45,067
kWh
$1,882
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,233 $600 $2,456
32,615
kWh
$777
-
kW-mo/yr
03 2.4133: Use most efficient type of electric motors $1,476 $4,242 $983
13,057
kWh
$493
-
kW-mo/yr
04 2.4231: Reduce the pressure of compressed air to the minimum required $718 - $718
9,545
kWh
-
05 2.7135: Install occupancy sensors $441 $540 $441
5,858
kWh
-
06 2.2511: Insulate bare equipment $142 $218 $142
1,888
kWh
-
TOTAL RECOMMENDED $11,286 $12,683 $8,134
108,030
kWh
$3,152
-
kW-mo/yr
TOTAL IMPLEMENTED $3,951 $600 $3,174
42,160
kWh
$777
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs