Assessment Year | 2018 |
---|---|
Principal Product | Metal Finishings |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 40 |
Plant Area |
25,000
ft2
|
Annual Production | 300,000
units
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $41,313 | 380,560 |
kWh
|
$0.11 |
Electricity Demand | $31,348 | 2,607 |
kW-mo/yr
|
$12.02 |
Electricity Fees | $9,084 | - |
|
- |
Natural Gas | $32,041 | 4,327 |
MMBtu
|
$7.41 |
TOTAL YEARLY COSTS | $113,786 | |||
RECOMMENDED SAVINGS* | $5,460 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,800 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,515 | $1,500 |
$1,515
13,946
kWh
|
- | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $1,493 | $3,414 |
$1,493
13,752
kWh
|
- | - | |
03 | 2.2511: Insulate bare equipment | $1,167 | $2,318 | - | - |
$1,167
-
MMBtu
|
|
04 | 2.4133: Use most efficient type of electric motors | $670 | $683 |
$406
3,734
kWh
|
$264
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $615 | $1,015 |
$615
5,659
kWh
|
- | - | |
TOTAL RECOMMENDED | $5,460 | $8,930 |
$4,029
37,091
kWh
|
$264
-
kW-mo/yr
|
$1,167
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,800 | $3,198 |
$2,536
23,339
kWh
|
$264
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs