Assessment Year | 2018 |
---|---|
Principal Product | Water Reclamation Plant |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $100 M to 500M |
# of Employees | 200 |
Plant Area |
1,500,000
ft2
|
Annual Production | 22,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,516,170 | 27,120,802 |
kWh
|
$0.056 |
Electricity Demand | $1 | 104,213 |
kW-mo/yr
|
$0.000 |
TOTAL YEARLY COSTS | $1,516,171 | |||
RECOMMENDED SAVINGS* | $34,207 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $21,844 | $45,396 |
$21,844
390,778
kWh
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,568 | $90,762 |
$11,568
206,946
kWh
|
|
03 | 2.4133: Use most efficient type of electric motors | $795 | $1,723 |
$795
14,214
kWh
|
|
TOTAL RECOMMENDED | $34,207 | $137,881 |
$34,207
611,938
kWh
|
||
TOTAL IMPLEMENTED | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs