Assessment Year | 2017 |
---|---|
Principal Product | Turbine component repair |
NAICS | 336412: Aircraft Engine and Engine Parts Manufacturing |
SIC | 3724: Aircraft Engines and Engine Parts |
Sales Range | $10 M to 50M |
# of Employees | 121 |
Plant Area |
100,000
ft2
|
Annual Production | 92,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $561,059 | 5,764,411 |
kWh
|
$0.097 |
Electricity Demand | $429,988 | 14,128 |
kW-mo/yr
|
$30.44 |
Electricity Fees | $(-54,560.0) | - |
|
- |
Natural Gas | $43,393 | 6,271 |
MMBtu
|
$6.92 |
TOTAL YEARLY COSTS | $979,880 | |||
RECOMMENDED SAVINGS* | $212,829 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $138,725 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3132: Recharge batteries on during off-peak demand periods | $57,756 | $205,000 |
$(-4,425.0)
(-45,625)
kWh
|
$62,181
-
kW-mo/yr
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $36,675 | $3,790 |
$34,560
355,187
kWh
|
$14,094
-
kW-mo/yr
|
$(-11,979.0)
-
MMBtu
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $23,797 | $36,600 |
$23,797
244,571
kWh
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,198 | $27,633 |
$11,549
118,696
kWh
|
$8,206
-
kW-mo/yr
|
- | $443 | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $20,046 | $53,400 |
$10,810
111,139
kWh
|
$9,236
-
kW-mo/yr
|
- | - | |
06 | 2.2514: Cover open tanks | $18,591 | $10,800 |
$18,591
191,061
kWh
|
- | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $17,514 | $21,100 |
$17,514
180,004
kWh
|
- | - | - | |
08 | 2.4322: Use or replace with energy efficient substitutes | $5,696 | $2,740 |
$5,696
58,542
kWh
|
- | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,278 | $16,770 |
$4,278
43,974
kWh
|
- | - | - | |
10 | 2.4239: Eliminate or reduce compressed air usage | $3,658 | $10,285 |
$3,658
37,590
kWh
|
- | - | - | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,718 | $1,300 |
$2,718
27,930
kWh
|
- | - | - | |
12 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,902 | $200 |
$1,902
19,551
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $212,829 | $389,618 |
$130,648
1,342,620
kWh
|
$93,717
-
kW-mo/yr
|
$(-11,979.0)
-
MMBtu
|
$443 | ||
TOTAL IMPLEMENTED | $138,725 | $319,433 |
$58,659
602,756
kWh
|
$79,623
-
kW-mo/yr
|
- | $443 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs