ITAC Assessment: SD0550
ITAC logo
ITAC Assessment: SD0550
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Dyed Textiles
NAICS 313310: Textile and Fabric Finishing Mills
SIC 2253: Knit Outerwear Mills
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 66,000
ft2
Annual Production 500,000
units
Production Hrs. Annual 8,640
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,540,249 14,012,111
kWh
Electricity Demand $538,379 36,239
kW-mo/yr
Electricity Fees $35,853 -
Natural Gas $594,020 423,079
MMBtu
Waste Disposal Costs
Water Usage $934,500 350,000
Tgal
TOTAL YEARLY COSTS $3,643,001
RECOMMENDED SAVINGS* $661,860 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $128,840

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $526,998 $1,348,560 $541,236
4,924,800
kWh
$106,992
-
kW-mo/yr
$(-98,496.0) $(-22,734.0)
-
MMBtu
-
02 3.4111: Use closed cycle process to minimize waste water production $119,615 $210,000 $(-17,309.0)
(-157,500)
kWh
$(-3,251.0)
-
kW-mo/yr
- - $140,175
-
Tgal
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,225 $2,500 $9,225
83,942
kWh
- - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $3,945 $600 $3,945
35,900
kWh
- - - -
05 2.2414: Use waste heat from hot flue gases to preheat $2,077 $9,750 - - - $2,077
-
MMBtu
-
TOTAL RECOMMENDED $661,860 $1,571,410 $537,097
4,887,142
kWh
$103,741
-
kW-mo/yr
$(-98,496.0) $(-20,657.0)
-
MMBtu
$140,175
-
Tgal
TOTAL IMPLEMENTED $128,840 $212,500 $(-8,084.0)
(-73,558)
kWh
$(-3,251.0)
-
kW-mo/yr
- - $140,175
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs