Assessment Year | 2017 |
---|---|
Principal Product | Data Center Cabinets |
NAICS | 332510: Hardware Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
38,000
ft2
|
Annual Production | 9,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $100,736 | 878,920 |
kWh
|
$0.11 |
Electricity Demand | $39,164 | 2,877 |
kW-mo/yr
|
$13.61 |
Electricity Fees | $21,318 | - |
|
- |
Natural Gas | $53,920 | 9,384 |
MMBtu
|
$5.75 |
TOTAL YEARLY COSTS | $215,138 | |||
RECOMMENDED SAVINGS* | $17,183 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,712 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,853 | $20,582 |
$4,617
40,292
kWh
|
$1,082
-
kW-mo/yr
|
- | $154 | |
02 | 2.7134: Use photocell controls | $3,679 | $11,568 |
$3,558
31,054
kWh
|
$121
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,165 | $1,500 |
$3,165
27,616
kWh
|
- | - | - | |
04 | 2.7135: Install occupancy sensors | $1,746 | $2,045 |
$1,746
15,236
kWh
|
- | - | - | |
05 | 2.2511: Insulate bare equipment | $1,326 | $750 |
$(-79.0)
(-686)
kWh
|
$(-33.0)
-
kW-mo/yr
|
$1,438
-
MMBtu
|
- | |
06 | 2.4239: Eliminate or reduce compressed air usage | $725 | $914 |
$725
6,322
kWh
|
- | - | - | |
07 | 2.4133: Use most efficient type of electric motors | $689 | $567 |
$558
4,868
kWh
|
$131
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $17,183 | $37,926 |
$14,290
124,702
kWh
|
$1,301
-
kW-mo/yr
|
$1,438
-
MMBtu
|
$154 | ||
TOTAL IMPLEMENTED | $14,712 | $34,967 |
$11,819
103,144
kWh
|
$1,301
-
kW-mo/yr
|
$1,438
-
MMBtu
|
$154 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs