Assessment Year | 2017 |
---|---|
Principal Product | Capacitor, Resistor, Coil, Transformer, and Other Inductors |
NAICS | 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing |
SIC | 3677: Electronic Coils, Transformers, and Other Inductors |
Sales Range | $10 M to 50M |
# of Employees | 198 |
Plant Area |
77,000
ft2
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $535,356 | 5,574,528 |
kWh
|
$0.096 |
Electricity Demand | $190,944 | 14,256 |
kW-mo/yr
|
$13.39 |
Electricity Fees | $113,865 | - |
|
- |
Natural Gas | $43,746 | 6,945 |
MMBtu
|
$6.30 |
TOTAL YEARLY COSTS | $883,911 | |||
RECOMMENDED SAVINGS* | $72,531 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $43,896 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $23,627 | $14,788 |
$24,607
256,333
kWh
|
$6,270
-
kW-mo/yr
|
$(-7,250.0)
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,529 | $41,589 |
$11,822
123,126
kWh
|
$3,170
-
kW-mo/yr
|
- | $537 | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,835 | $26,705 |
$10,120
105,417
kWh
|
$2,715
-
kW-mo/yr
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $5,488 | $8,800 |
$4,327
45,061
kWh
|
$1,161
-
kW-mo/yr
|
- | - | |
05 | 2.2522: Isolate hot or cold equipment | $5,008 | $2,160 |
$3,949
41,137
kWh
|
$1,059
-
kW-mo/yr
|
- | - | |
06 | 2.4322: Use or replace with energy efficient substitutes | $3,765 | $3,500 |
$2,956
30,793
kWh
|
$809
-
kW-mo/yr
|
- | - | |
07 | 2.7134: Use photocell controls | $3,481 | $10,611 |
$3,342
34,824
kWh
|
$139
-
kW-mo/yr
|
- | - | |
08 | 2.2693: Use waste heat steam for absorption refrigeration | $2,798 | $7,832 |
$2,206
22,984
kWh
|
$592
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $72,531 | $115,985 |
$63,329
659,675
kWh
|
$15,915
-
kW-mo/yr
|
$(-7,250.0)
-
MMBtu
|
$537 | ||
TOTAL IMPLEMENTED | $43,896 | $99,037 |
$34,773
362,205
kWh
|
$8,586
-
kW-mo/yr
|
- | $537 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs