ITAC Assessment: SD0544
ITAC logo
ITAC Assessment: SD0544
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Capacitor, Resistor, Coil, Transformer, and Other Inductors
NAICS 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing
SIC 3677: Electronic Coils, Transformers, and Other Inductors
Sales Range $10
M
to 50
M
# of Employees 198
Plant Area 77,000
ft2
Annual Production 2,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $535,356 5,574,528
kWh
Electricity Demand $190,944 14,256
kW-mo/yr
Electricity Fees $113,865 -
Natural Gas $43,746 6,945
MMBtu
TOTAL YEARLY COSTS $883,911
RECOMMENDED SAVINGS* $72,531 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $43,896

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $23,627 $14,788 $24,607
256,333
kWh
$6,270
-
kW-mo/yr
$(-7,250.0)
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $15,529 $41,589 $11,822
123,126
kWh
$3,170
-
kW-mo/yr
- $537
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $12,835 $26,705 $10,120
105,417
kWh
$2,715
-
kW-mo/yr
- -
04 2.4133: Use most efficient type of electric motors $5,488 $8,800 $4,327
45,061
kWh
$1,161
-
kW-mo/yr
- -
05 2.2522: Isolate hot or cold equipment $5,008 $2,160 $3,949
41,137
kWh
$1,059
-
kW-mo/yr
- -
06 2.4322: Use or replace with energy efficient substitutes $3,765 $3,500 $2,956
30,793
kWh
$809
-
kW-mo/yr
- -
07 2.7134: Use photocell controls $3,481 $10,611 $3,342
34,824
kWh
$139
-
kW-mo/yr
- -
08 2.2693: Use waste heat steam for absorption refrigeration $2,798 $7,832 $2,206
22,984
kWh
$592
-
kW-mo/yr
- -
TOTAL RECOMMENDED $72,531 $115,985 $63,329
659,675
kWh
$15,915
-
kW-mo/yr
$(-7,250.0)
-
MMBtu
$537
TOTAL IMPLEMENTED $43,896 $99,037 $34,773
362,205
kWh
$8,586
-
kW-mo/yr
- $537
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs