| Assessment Year | 2017 |
|---|---|
| Principal Product | Adhesives and Sealants |
| NAICS | 325520: Adhesive Manufacturing |
| SIC | 2891: Adhesives and Sealants |
| Sales Range | $10 M to 50M |
| # of Employees | 57 |
| Plant Area |
125,000
ft2
|
| Annual Production | 42,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $143,054 | 1,950,307 |
kWh
|
$0.073 |
| Electricity Demand | $146,052 | 5,759 |
kW-mo/yr
|
$25.36 |
| Electricity Fees | $7,947 | - |
|
- |
| Natural Gas | $12,896 | 1,955 |
MMBtu
|
$6.60 |
| TOTAL YEARLY COSTS | $309,949 | |||
| RECOMMENDED SAVINGS* | $128,185 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $42,256 | $168,000 |
$13,438
183,325
kWh
|
$28,818
-
kW-mo/yr
|
- | - | |
| 02 | 2.3137: Use power during off-peak periods | $33,558 | $136,000 |
$(-1,372.0)
(-18,720)
kWh
|
$35,930
-
kW-mo/yr
|
$(-1,000.0) | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,953 | $11,528 |
$13,783
188,030
kWh
|
$9,170
-
kW-mo/yr
|
- | - | |
| 04 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $17,767 | $20,883 |
$1,988
27,118
kWh
|
$15,779
-
kW-mo/yr
|
- | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,414 | $16,180 |
$2,679
36,546
kWh
|
$1,735
-
kW-mo/yr
|
- | - | |
| 06 | 2.7134: Use photocell controls | $2,234 | $7,400 |
$2,022
27,590
kWh
|
$212
-
kW-mo/yr
|
- | - | |
| 07 | 2.3212: Optimize plant power factor | $1,665 | $5,360 | - | - | $1,665 | - | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,457 | $1,100 |
$503
6,862
kWh
|
$954
-
kW-mo/yr
|
- | - | |
| 09 | 2.7241: Install outside air damper / economizer on hvac unit | $950 | $2,520 | - | - | - |
$950
-
MMBtu
|
|
| 10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $931 | $200 |
$931
12,699
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $128,185 | $369,171 |
$33,972
463,450
kWh
|
$92,598
-
kW-mo/yr
|
$665 |
$950
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs