ITAC Assessment: SD0536
ITAC logo
ITAC Assessment: SD0536
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Steel Wire Drawing and Other Fabricated Wire Products
NAICS 332618: Other Fabricated Wire Product Manufacturing
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 80,000
ft2
Annual Production 150
units
Production Hrs. Annual 7,200
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $102,866 1,363,143
kWh
Electricity Demand $93,723 3,710
kW-mo/yr
Electricity Fees $7,363 -
Natural Gas $173,184 30,247
MMBtu
TOTAL YEARLY COSTS $377,136
RECOMMENDED SAVINGS* $144,781 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,365

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $91,093 $350,298 $68,332
1,231,200
kWh
$54,562
-
kW-mo/yr
$(-31,801.0)
-
MMBtu
-
02 4.131: Modify process to reduce material use/cost $23,163 $68,259 - - $(-1,837.0)
-
MMBtu
$25,000
03 2.7142: Utilize higher efficiency lamps and/or ballasts $7,468 $8,787 $4,682
62,007
kWh
$2,786
-
kW-mo/yr
- -
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $6,259 $11,760 $2,705
35,839
kWh
$3,554
-
kW-mo/yr
- -
05 2.2414: Use waste heat from hot flue gases to preheat $5,594 $11,180 - - $5,594
-
MMBtu
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,995 $648 $2,184
28,927
kWh
$811
-
kW-mo/yr
- -
07 2.7134: Use photocell controls $2,367 $3,700 $2,022
26,775
kWh
$345
-
kW-mo/yr
- -
08 2.2511: Insulate bare equipment $1,796 $2,742 - - $1,796
-
MMBtu
-
09 2.4231: Reduce the pressure of compressed air to the minimum required $1,472 $200 $1,472
19,496
kWh
- - -
10 2.7135: Install occupancy sensors $1,296 $3,200 $1,296
17,170
kWh
- - -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,278 $1,200 $768
10,174
kWh
$510
-
kW-mo/yr
- -
TOTAL RECOMMENDED $144,781 $461,974 $83,461
1,431,588
kWh
$62,568
-
kW-mo/yr
$(-26,248.0)
-
MMBtu
$25,000
TOTAL IMPLEMENTED $7,365 $7,790 $4,248
56,271
kWh
$1,321
-
kW-mo/yr
$1,796
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs