Assessment Year | 2016 |
---|---|
Principal Product | Steel Wire Drawing and Other Fabricated Wire Products |
NAICS | 332618: Other Fabricated Wire Product Manufacturing |
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
80,000
ft2
|
Annual Production | 150
units
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $102,866 | 1,363,143 |
kWh
|
$0.075 |
Electricity Demand | $93,723 | 3,710 |
kW-mo/yr
|
$25.26 |
Electricity Fees | $7,363 | - |
|
- |
Natural Gas | $173,184 | 30,247 |
MMBtu
|
$5.73 |
TOTAL YEARLY COSTS | $377,136 | |||
RECOMMENDED SAVINGS* | $144,781 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,365 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $91,093 | $350,298 |
$68,332
1,231,200
kWh
|
$54,562
-
kW-mo/yr
|
$(-31,801.0)
-
MMBtu
|
- | |
02 | 4.131: Modify process to reduce material use/cost | $23,163 | $68,259 | - | - |
$(-1,837.0)
-
MMBtu
|
$25,000 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,468 | $8,787 |
$4,682
62,007
kWh
|
$2,786
-
kW-mo/yr
|
- | - | |
04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $6,259 | $11,760 |
$2,705
35,839
kWh
|
$3,554
-
kW-mo/yr
|
- | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $5,594 | $11,180 | - | - |
$5,594
-
MMBtu
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,995 | $648 |
$2,184
28,927
kWh
|
$811
-
kW-mo/yr
|
- | - | |
07 | 2.7134: Use photocell controls | $2,367 | $3,700 |
$2,022
26,775
kWh
|
$345
-
kW-mo/yr
|
- | - | |
08 | 2.2511: Insulate bare equipment | $1,796 | $2,742 | - | - |
$1,796
-
MMBtu
|
- | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,472 | $200 |
$1,472
19,496
kWh
|
- | - | - | |
10 | 2.7135: Install occupancy sensors | $1,296 | $3,200 |
$1,296
17,170
kWh
|
- | - | - | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,278 | $1,200 |
$768
10,174
kWh
|
$510
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $144,781 | $461,974 |
$83,461
1,431,588
kWh
|
$62,568
-
kW-mo/yr
|
$(-26,248.0)
-
MMBtu
|
$25,000 | ||
TOTAL IMPLEMENTED | $7,365 | $7,790 |
$4,248
56,271
kWh
|
$1,321
-
kW-mo/yr
|
$1,796
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs