Assessment Year | 2002 |
---|---|
Principal Product | Calcium Carbonate |
NAICS |
n/a
|
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
103,625
ft2
|
Annual Production | 600,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $587,155 | 11,701,316 |
kWh
|
$0.050 |
Natural Gas | $165,436 | 18,946 |
MMBtu
|
$8.73 |
Fuel Oil #1 | $14,300 | 1,316 |
MMBtu
|
$10.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $116,847 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,274 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $55,394 | - | - | - | - | - | $55,394 | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $388 | $250 |
$388
12,348
kWh
|
- | - | - | - | |
03 | 2.7134: Use photocell controls | $3,933 | $2,675 |
$3,933
106,290
kWh
|
- | - | - | - | |
04 | 2.1331: Burn a less expensive grade of fuel | $21,246 | $9,000 | - | - |
$6,946
-
MMBtu
|
$14,300
-
MMBtu
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,330 | $550 |
$1,330
40,100
kWh
|
- | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $21,556 | $131,786 |
$21,556
686,502
kWh
|
- | - | - | - | |
07 | 2.8114: Change rate schedules or other changes in utility service | $13,000 | - | - |
$13,000
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $116,847 | $144,261 |
$27,207
845,240
kWh
|
$13,000
-
kW-mo/yr
|
$6,946
-
MMBtu
|
$14,300
-
MMBtu
|
$55,394 | ||
TOTAL IMPLEMENTED | $23,274 | $132,586 |
$23,274
738,950
kWh
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs