Assessment Year | 2016 |
---|---|
Principal Product | Injection Molded Plastics |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
45,000
ft2
|
Annual Production | 80,001
units
|
Production Hrs. Annual | 7,350
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $129,611 | 1,482,967 |
kWh
|
$0.087 |
Electricity Demand | $122,750 | 4,855 |
kW-mo/yr
|
$25.28 |
Electricity Fees | $6,638 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $114,694 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $63,923 | $80,120 |
$40,133
459,193
kWh
|
$33,582
-
kW-mo/yr
|
$(-9,792.0)
-
MMBtu
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,324 | $35,903 |
$6,793
77,713
kWh
|
$3,248
-
kW-mo/yr
|
- | - | $6,283 | |
03 | 3.5311: Recover and reuse waste material | $11,486 | $5,500 |
$(-34.0)
(-381)
kWh
|
- | - | $11,520 | - | |
04 | 2.7135: Install occupancy sensors | $8,590 | $4,950 |
$8,590
98,285
kWh
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,749 | $1,000 |
$3,171
36,280
kWh
|
$1,578
-
kW-mo/yr
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,938 | $800 |
$2,938
33,619
kWh
|
- | - | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,421 | $3,450 |
$1,863
21,327
kWh
|
$558
-
kW-mo/yr
|
- | - | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $2,279 | $1,300 |
$643
7,352
kWh
|
$1,636
-
kW-mo/yr
|
- | - | - | |
09 | 2.7145: Install skylights | $1,418 | $3,648 |
$1,016
11,629
kWh
|
$402
-
kW-mo/yr
|
- | - | - | |
10 | 2.2511: Insulate bare equipment | $566 | $203 |
$566
6,475
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $114,694 | $136,874 |
$65,679
751,492
kWh
|
$41,004
-
kW-mo/yr
|
$(-9,792.0)
-
MMBtu
|
$11,520 | $6,283 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs