| Assessment Year | 2015 |
|---|---|
| Principal Product | Hand Bags |
| NAICS | 316992: Women's Handbag and Purse Manufacturing |
| SIC | 3171: Women's Handbags and Purses |
| Sales Range | $10 M to 50M |
| # of Employees | 500 |
| Plant Area |
110,000
ft2
|
| Annual Production | 460,000
pieces
|
| Production Hrs. Annual | 2,388
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $254,131 | 2,806,535 |
kWh
|
$0.091 |
| Electricity Demand | $241,878 | 11,249 |
kW-mo/yr
|
$21.50 |
| Electricity Fees | $31,668 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,806 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,964 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $9,509 | $14,580 |
$4,861
53,711
kWh
|
$4,648
-
kW-mo/yr
|
- | |
| 02 | 2.7273: Install desiccant humidity control system | $8,026 | $34,300 |
$4,795
52,984
kWh
|
$4,369
-
kW-mo/yr
|
$(-1,138.0)
-
Tgal
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,823 | $1,400 |
$2,628
29,031
kWh
|
$1,195
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $1,368 | $3,042 |
$1,368
15,127
kWh
|
- | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $1,141 | $1,250 |
$520
5,751
kWh
|
$621
-
kW-mo/yr
|
- | |
| 06 | 2.6218: Turn off equipment when not in use | $939 | $200 |
$260
2,870
kWh
|
$679
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $24,806 | $54,772 |
$14,432
159,474
kWh
|
$11,512
-
kW-mo/yr
|
$(-1,138.0)
-
Tgal
|
||
| TOTAL IMPLEMENTED | $4,964 | $2,650 |
$3,148
34,782
kWh
|
$1,816
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs