Assessment Year | 2014 |
---|---|
Principal Product | treated sewage water |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 6 |
Plant Area |
600,000
ft2
|
Annual Production | 730,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $132,386 | 1,953,995 |
kWh
|
$0.068 |
Electricity Demand | $53,047 | 4,355 |
kW-mo/yr
|
$12.18 |
Electricity Fees | $3,626 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $88,765 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,419 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $55,346 | $151,250 |
$76,171
1,123,470
kWh
|
$16,443
-
kW-mo/yr
|
$(-37,268.0)
-
MMBtu
|
|
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $13,532 | $99,966 |
$1,536
-
kWh
|
$11,996
-
kW-mo/yr
|
- | |
03 | 2.4321: Upgrade obsolete equipment | $9,337 | $35,560 |
$9,337
137,709
kWh
|
- | - | |
04 | 3.1192: Reduce scrap production | $4,795 | $10,700 |
$3,779
55,742
kWh
|
$1,016
-
kW-mo/yr
|
- | |
05 | 2.4131: Size electric motors for peak operating efficiency | $3,282 | $9,400 |
$2,895
42,702
kWh
|
$387
-
kW-mo/yr
|
- | |
06 | 2.4131: Size electric motors for peak operating efficiency | $2,473 | $2,350 |
$1,985
29,270
kWh
|
$488
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $88,765 | $309,226 |
$95,703
1,388,893
kWh
|
$30,330
-
kW-mo/yr
|
$(-37,268.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $33,419 | $157,976 |
$19,532
265,423
kWh
|
$13,887
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs