ITAC Assessment: SD0486
ITAC logo
ITAC Assessment: SD0486
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product aerospace clamps
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 255
Plant Area 88,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 5,434
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $259,309 3,386,554
kWh
Electricity Demand $246,981 9,979
kW-mo/yr
Electricity Fees $33,312 -
Natural Gas $32,375 4,545
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $191,062 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7233: Use properly designed and sized hvac equipment $75,586 $286,300 $63,933
834,645
kWh
$11,653
-
kW-mo/yr
02 2.7425: Clean or color roof to reduce solar load $54,581 $250,000 $37,904
494,828
kWh
$16,677
-
kW-mo/yr
03 3.1192: Reduce scrap production $29,967 $30,993 $29,967
391,215
kWh
-
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $14,957 $4,985 - $14,957
-
kW-mo/yr
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $13,274 $22,000 $10,579
138,112
kWh
$2,695
-
kW-mo/yr
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,270 $600 $1,674
21,855
kWh
$596
-
kW-mo/yr
07 2.4231: Reduce the pressure of compressed air to the minimum required $427 $600 $316
4,121
kWh
$111
-
kW-mo/yr
TOTAL RECOMMENDED $191,062 $595,478 $144,373
1,884,776
kWh
$46,689
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs