| Assessment Year | 2013 |
|---|---|
| Principal Product | tortillas |
| NAICS | 311830: Tortilla Manufacturing |
| SIC | 2041: Flour and Other Grain Mill Products |
| Sales Range | $10 M to 50M |
| # of Employees | 136 |
| Plant Area |
75,000
ft2
|
| Annual Production | 150,000,000
pieces
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $175,945 | 2,444,404 |
kWh
|
$0.072 |
| Electricity Demand | $81,503 | 5,829 |
kW-mo/yr
|
$13.98 |
| Electricity Fees | $12,795 | - |
|
- |
| Natural Gas | $81,947 | 14,797 |
MMBtu
|
$5.54 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $45,336 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,731 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4134: Replace electric motor with fossil fuel engine | $18,166 | $60,710 |
$30,688
426,222
kWh
|
$14,324
-
kW-mo/yr
|
$(-26,846.0)
-
MMBtu
|
|
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $16,606 | $29,550 |
$17,276
239,937
kWh
|
$5,375
-
kW-mo/yr
|
$(-6,045.0)
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,054 | $2,000 |
$3,732
51,836
kWh
|
$2,322
-
kW-mo/yr
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,677 | $200 |
$1,677
23,289
kWh
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $1,318 | $1,521 |
$1,318
18,303
kWh
|
- | - | |
| 06 | 2.4226: Use / purchase optimum sized compressor | $1,113 | $200 |
$849
11,796
kWh
|
$264
-
kW-mo/yr
|
- | |
| 07 | 2.7134: Use photocell controls | $402 | $1,100 |
$307
4,262
kWh
|
$95
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $45,336 | $95,281 |
$55,847
775,645
kWh
|
$22,380
-
kW-mo/yr
|
$(-32,891.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $7,731 | $2,200 |
$5,409
75,125
kWh
|
$2,322
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs