Assessment Year | 2011 |
---|---|
Principal Product | Gas Turbine Engines |
NAICS | 334519: Other Measuring and Controlling Device Manufacturing |
SIC | 3829: Measuring and Controlling Devices, Not Elsewhere Classified |
Sales Range | greater than $500 M |
# of Employees | 750 |
Plant Area |
270,000
ft2
|
Annual Production | 5,000
units
|
Production Hrs. Annual | 5,616
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $596,733 | 5,856,033 |
kWh
|
$0.10 |
Electricity Demand | $249,572 | 15,467 |
kW-mo/yr
|
$16.14 |
Electricity Fees | $55,368 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $304,239 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,054 | $100 |
$2,054
20,159
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,678 | $700 |
$4,661
45,745
kWh
|
$1,017
-
kW-mo/yr
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,510 | $5,375 |
$16,510
162,026
kWh
|
- | |
04 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $5,851 | $8,326 |
$4,253
41,735
kWh
|
$1,598
-
kW-mo/yr
|
|
05 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $110,990 | $185,200 |
$110,990
1,089,207
kWh
|
- | |
06 | 2.2437: Recover waste heat from equipment | $163,156 | $302,600 |
$163,156
1,601,134
kWh
|
- | |
TOTAL RECOMMENDED | $304,239 | $502,301 |
$301,624
2,960,006
kWh
|
$2,615
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs