Assessment Year | 2011 |
---|---|
Principal Product | Propulsion Engines |
NAICS | 334519: Other Measuring and Controlling Device Manufacturing |
SIC | 3829: Measuring and Controlling Devices, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 1,200 |
Plant Area |
326,000
ft2
|
Annual Production | 30
pieces
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,512,268 | 17,853,182 |
kWh
|
$0.085 |
Electricity Demand | $497,564 | 38,882 |
kW-mo/yr
|
$12.80 |
Electricity Fees | $311,693 | - |
|
- |
Natural Gas | $179,095 | 26,225 |
MMBtu
|
$6.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $89,587 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,716 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,004 | $300 |
$1,661
19,605
kWh
|
$344
-
kW-mo/yr
|
- | - | |
02 | 2.2514: Cover open tanks | $36,210 | $16,850 |
$17,462
206,167
kWh
|
- | - |
$18,748
-
MMBtu
|
|
03 | 2.6231: Utilize controls to operate equipment only when needed | $1,445 | $1,530 |
$1,445
17,063
kWh
|
- | - | - | |
04 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $28,654 | $53,450 |
$28,654
338,305
kWh
|
- | - | - | |
05 | 2.3212: Optimize plant power factor | $12,712 | $37,600 | - | - | $12,712 | - | |
06 | 2.7145: Install skylights | $8,562 | $25,530 |
$5,977
67,770
kWh
|
$2,585
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $89,587 | $135,260 |
$55,199
648,910
kWh
|
$2,928
-
kW-mo/yr
|
$12,712 |
$18,748
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,716 | $37,900 |
$1,661
19,605
kWh
|
$344
-
kW-mo/yr
|
$12,712 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs