| Assessment Year | 2011 |
|---|---|
| Principal Product | Aerospace Sealants |
| NAICS | 325520: Adhesive Manufacturing |
| SIC | 2891: Adhesives and Sealants |
| Sales Range | $1 M to 5M |
| # of Employees | 95 |
| Plant Area |
50,000
ft2
|
| Annual Production | 1,000
units
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $135,564 | 1,504,708 |
kWh
|
$0.090 |
| Electricity Demand | $57,554 | 4,347 |
kW-mo/yr
|
$13.24 |
| Electricity Fees | $24,390 | - |
|
- |
| Natural Gas | $12,428 | 1,549 |
MMBtu
|
$8.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $70,234 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $61,452 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $3,036 | - |
$3,036
33,696
kWh
|
- | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $58,730 | $2,850 |
$69,614
772,632
kWh
|
$14,000
-
kW-mo/yr
|
$(-24,884.0)
-
MMBtu
|
|
| 03 | 2.7135: Install occupancy sensors | $3,552 | $214 |
$3,552
39,424
kWh
|
- | - | |
| 04 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $2,194 | $610 |
$2,194
24,353
kWh
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,326 | $700 |
$1,104
12,250
kWh
|
$222
-
kW-mo/yr
|
- | |
| 06 | 2.2437: Recover waste heat from equipment | $1,396 | $2,000 |
$1,396
15,489
kWh
|
- | - | |
| TOTAL RECOMMENDED | $70,234 | $6,374 |
$80,896
897,844
kWh
|
$14,222
-
kW-mo/yr
|
$(-24,884.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $61,452 | $5,550 |
$72,114
800,371
kWh
|
$14,222
-
kW-mo/yr
|
$(-24,884.0)
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs