Assessment Year | 2009 |
---|---|
Principal Product | COOKIES AND CRACKERS |
NAICS | 311821: Cookie and Cracker Manufacturing |
SIC | 2052: Cookies and Crackers |
Sales Range | less than $500 k |
# of Employees | 700 |
Plant Area |
150,000
ft2
|
Annual Production | 450
units
|
Production Hrs. Annual | 5,824
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $754,508 | 8,447,220 |
kWh
|
$0.089 |
Electricity Demand | $225,737 | 19,543 |
kW-mo/yr
|
$11.55 |
Electricity Fees | $141 | - |
|
- |
Natural Gas | $566,911 | 59,831 |
MMBtu
|
$9.48 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $511,167 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $49,401 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,500 | $6,463 |
$14,500
162,926
kWh
|
- | - | |
02 | 2.1221: Replace obsolete burners with more efficient ones | $35,684 | $50,000 | - | - |
$35,684
-
MMBtu
|
|
03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $94,850 | $12,450 | - | - |
$94,850
-
MMBtu
|
|
04 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $269,651 | $1,430,000 |
$269,651
8,760,000
kWh
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,149 | $2,700 |
$13,149
147,741
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,991 | $16,630 |
$18,676
209,140
kWh
|
$3,315
-
kW-mo/yr
|
- | |
07 | 2.2622: Replace existing chiller with high efficiency model | $60,774 | $175,800 |
$48,011
537,636
kWh
|
$12,763
-
kW-mo/yr
|
- | |
08 | 2.4133: Use most efficient type of electric motors | $568 | $1,444 |
$325
3,640
kWh
|
$243
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $511,167 | $1,695,487 |
$364,312
9,821,083
kWh
|
$16,321
-
kW-mo/yr
|
$130,534
-
MMBtu
|
||
TOTAL IMPLEMENTED | $49,401 | $54,144 |
$13,474
151,381
kWh
|
$243
-
kW-mo/yr
|
$35,684
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs