Assessment Year | 2007 |
---|---|
Principal Product | SPAS Vacuum Thermoformed Acrylic |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
134,936
ft2
|
Annual Production | 12,000
pieces
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $169,685 | 2,116,205 |
kWh
|
$0.080 |
Electricity Demand | $115,454 | 7,950 |
kW-mo/yr
|
$14.52 |
Electricity Fees | $13,764 | - |
|
- |
Natural Gas | $37,420 | 3,989 |
MMBtu
|
$9.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,247 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,849 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,816 | $8,425 |
$10,816
65,332
kWh
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,658 | $13,350 |
$5,658
44,268
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,155 | $240 |
$2,497
31,160
kWh
|
$2,658
-
kW-mo/yr
|
- | |
04 | 2.2437: Recover waste heat from equipment | $4,081 | $1,213 | - | - |
$4,081
-
MMBtu
|
|
05 | 2.7135: Install occupancy sensors | $3,878 | $3,400 |
$1,563
19,480
kWh
|
$2,315
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $659 | $1,146 |
$659
8,223
kWh
|
- | - | |
TOTAL RECOMMENDED | $30,247 | $27,774 |
$21,193
168,463
kWh
|
$4,973
-
kW-mo/yr
|
$4,081
-
MMBtu
|
||
TOTAL IMPLEMENTED | $19,849 | $12,065 |
$14,876
115,972
kWh
|
$4,973
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs