ITAC Assessment: SD0392
ITAC logo
ITAC Assessment: SD0392
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Forged Aluminum Wheels
NAICS 336991: Motorcycle, Bicycle, and Parts Manufacturing
SIC 3751: Motorcycles, Bicycles, and Parts
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 150,000
ft2
Annual Production 14,000
pieces
Production Hrs. Annual 6,120
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $195,693 1,971,258
kWh
Electricity Demand $72,730 4,416
kW-mo/yr
Electricity Fees $10,654 -
Natural Gas $5,569 502
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,624 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,246 $20,870 $10,754
108,300
kWh
$3,492
-
kW-mo/yr
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,991 $7,991 $7,991
109,209
kWh
-
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $5,417 $17,500 $5,417
45,410
kWh
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,970 - $1,970
19,847
kWh
-
TOTAL RECOMMENDED $29,624 $46,361 $26,132
282,766
kWh
$3,492
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs