ITAC Assessment: SD0391
ITAC logo
ITAC Assessment: SD0391
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product aerosol can packaging
NAICS 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 30
Plant Area 45,000
ft2
Annual Production 18,500,000
pieces
Production Hrs. Annual 2,100
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $146,467 750,813
kWh
Natural Gas $13,171 1,218
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,037 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,709

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,231 $22,654 $4,316
43,160
kWh
$2,915
-
kW-mo/yr
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,478 $11,028 $6,478
63,643
kWh
- -
03 2.7134: Use photocell controls $5,850 $3,230 $2,514
24,700
kWh
$3,336
-
kW-mo/yr
-
04 2.2437: Recover waste heat from equipment $1,437 $2,332 - - $1,437
-
MMBtu
05 2.7135: Install occupancy sensors $1,041 $1,664 $1,041
10,405
kWh
- -
TOTAL RECOMMENDED $22,037 $40,908 $14,349
141,908
kWh
$6,251
-
kW-mo/yr
$1,437
-
MMBtu
TOTAL IMPLEMENTED $13,709 $33,682 $10,794
106,803
kWh
$2,915
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs