ITAC Assessment: SD0384
ITAC logo
ITAC Assessment: SD0384
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product limestone
NAICS 212312: Crushed and Broken Limestone Mining and Quarrying
SIC 1422: Crushed and Broken Limestone
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 2,400,000
ft2
Annual Production 1,404,000
ton
Production Hrs. Annual 8,736
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,294,047 34,543,672
kWh
Electricity Demand $436,915 55,943
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $522,653 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $199,400 $80,665 $171,738
2,586,423
kWh
$27,662
-
kW-mo/yr
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $184,174 $85,865 $158,614
2,388,734
kWh
$25,560
-
kW-mo/yr
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $115,354 $45,825 $99,345
1,496,149
kWh
$16,009
-
kW-mo/yr
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $20,082 $13,481 $20,082
302,443
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,401 - $2,401
36,146
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,242 $5,792 $1,072
16,144
kWh
$170
-
kW-mo/yr
TOTAL RECOMMENDED $522,653 $231,628 $453,252
6,826,039
kWh
$69,401
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs