Assessment Year | 2006 |
---|---|
Principal Product | aluminum forgings |
NAICS | 332112: Nonferrous Forging |
SIC | 3463: Nonferrous Forgings |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
100,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 0
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $474,210 | 6,451,835 |
kWh
|
$0.074 |
Electricity Demand | $333,201 | 18,975 |
kW-mo/yr
|
$17.56 |
Natural Gas | $1,229,510 | 135,111 |
MMBtu
|
$9.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $79,353 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $33,958 | - |
$25,318
344,468
kWh
|
$8,640
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,420 | $260 |
$11,976
162,943
kWh
|
$5,444
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,249 | $26,550 |
$14,249
193,867
kWh
|
- | - | |
04 | 2.4238: Do not use compressed air for personal cooling | $5,803 | $900 |
$5,803
78,957
kWh
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,966 | $4,300 |
$3,966
53,972
kWh
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $3,957 | $4,270 | - | - |
$3,957
-
MMBtu
|
|
TOTAL RECOMMENDED | $79,353 | $36,280 |
$61,312
834,207
kWh
|
$14,084
-
kW-mo/yr
|
$3,957
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs