ITAC Assessment: SD0380
ITAC logo
ITAC Assessment: SD0380
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product window blinds
NAICS 337920: Blind and Shade Manufacturing
SIC 2591: Drapery Hardware and Window Blinds and Shades
Sales Range $100
M
to 500
M
# of Employees 377
Plant Area 201,000
ft2
Annual Production 0
units
Production Hrs. Annual 3,438
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $161,823 2,444,449
kWh
Electricity Demand $52,930 6,628
kW-mo/yr
Natural Gas $8,068 859
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,722 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $11,026 $3,850 $7,758
117,193
kWh
$3,268
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,324 $220 $1,637
24,726
kWh
$687
-
kW-mo/yr
03 2.4239: Eliminate or reduce compressed air usage $1,495 $4,550 $1,495
22,578
kWh
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,418 $2,325 $1,418
21,427
kWh
-
05 2.7141: Lower light fixtures in high ceiling areas $459 $3,193 $323
4,879
kWh
$136
-
kW-mo/yr
TOTAL RECOMMENDED $16,722 $14,138 $12,631
190,803
kWh
$4,091
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs