Assessment Year | 1998 |
---|---|
Principal Product | Formed Metal products |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 76 |
Plant Area |
70,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $187,233 | 2,713,072 |
kWh
|
$0.069 |
Electricity Demand | $55,977 | 6,883 |
kW-mo/yr
|
$8.13 |
Natural Gas | $31,977 | 5,825 |
MMBtu
|
$5.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $77,301 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $36,824 | $4,285 | - |
$8,232
-
kW-mo/yr
|
$28,592
-
MMBtu
|
- | - | - | |
02 | 2.6218: Turn off equipment when not in use | $14,302 | - | - | - |
$14,302
-
MMBtu
|
- | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $7,246 | $1,800 | - |
$1,756
-
kW-mo/yr
|
$5,490
-
MMBtu
|
- | - | - | |
04 | 2.7229: Air condition only space necessary | $2,456 | $895 |
$1,334
19,343
kWh
|
$1,122
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.6218: Turn off equipment when not in use | $254 | - |
$205
2,931
kWh
|
$49
-
kW-mo/yr
|
- | - | - | - | |
06 | 3.4113: Treat and reuse rinse waters | $2,126 | $300 | - | - | - |
$2,126
-
Tgal
|
- | - | |
07 | 3.6112: Use filter and drying oven to reduce sludge volume | $12,929 | $8,000 | - | - | - | - |
$12,929
-
gal
|
- | |
08 | 4.711: Initiate a total quality management program | $1,164 | - | - | - | - | - | - | $1,164 | |
TOTAL RECOMMENDED | $77,301 | $15,280 |
$1,539
22,274
kWh
|
$11,159
-
kW-mo/yr
|
$48,384
-
MMBtu
|
$2,126
-
Tgal
|
$12,929
-
gal
|
$1,164 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs