Assessment Year | 2005 |
---|---|
Principal Product | Precision Aluminum Forgings |
NAICS | 332112: Nonferrous Forging |
SIC | 3463: Nonferrous Forgings |
Sales Range | $10 M to 50M |
# of Employees | 98 |
Plant Area |
175,564
ft2
|
Annual Production | 6,000,000
lb
|
Production Hrs. Annual | 5,250
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $324,730 | 3,660,402 |
kWh
|
$0.089 |
Electricity Demand | $161,275 | 13,646 |
kW-mo/yr
|
$11.82 |
Natural Gas | $318,764 | 4,241 |
MMBtu
|
$75.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $126,894 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,696 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $16,903 | $13,350 |
$13,759
155,120
kWh
|
$3,144
-
kW-mo/yr
|
- | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,954 | $7,595 |
$6,862
77,358
kWh
|
$2,092
-
kW-mo/yr
|
- | - | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $7,356 | $14,145 | - | - |
$7,356
-
MMBtu
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,793 | $3,000 |
$1,793
20,209
kWh
|
- | - | - | - | |
05 | 2.2511: Insulate bare equipment | $6,983 | $537 |
$6,983
7,812
kWh
|
- | - | - | - | |
06 | 2.7135: Install occupancy sensors | $2,079 | $3,500 |
$2,079
23,436
kWh
|
- | - | - | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,700 | $18,500 | - | - | - | - | $5,700 | |
08 | 4.445: Install equipment to move product | $77,126 | $70,000 | - | - | - | $77,126 | - | |
TOTAL RECOMMENDED | $126,894 | $130,627 |
$31,476
283,935
kWh
|
$5,236
-
kW-mo/yr
|
$7,356
-
MMBtu
|
$77,126 | $5,700 | ||
TOTAL IMPLEMENTED | $18,696 | $16,350 |
$15,552
175,329
kWh
|
$3,144
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs