Assessment Year | 2004 |
---|---|
Principal Product | Mattresses and Bedsprings |
NAICS | 337910: Mattress Manufacturing |
SIC | 2515: Mattresses, Foundations, and Convertible Beds |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
160,000
ft2
|
Annual Production | 800,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $231,626 | 4,256,800 |
kWh
|
$0.054 |
Electricity Demand | $20,375 | 18,653 |
kW-mo/yr
|
$1.09 |
Electricity Fees | $32,138 | - |
|
- |
Natural Gas | $7,139 | 763 |
MMBtu
|
$9.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,761 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,439 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,031 | $120 |
$585
16,341
kWh
|
$446
-
kW-mo/yr
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,011 | $15 |
$2,813
78,643
kWh
|
$2,198
-
kW-mo/yr
|
|
03 | 2.7135: Install occupancy sensors | $639 | $1,350 |
$639
17,824
kWh
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $205 | $254 |
$86
2,402
kWh
|
$119
-
kW-mo/yr
|
|
05 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $7,680 | $2,000 |
$7,680
175,200
kWh
|
- | |
06 | 2.4133: Use most efficient type of electric motors | $437 | $850 |
$229
6,372
kWh
|
$208
-
kW-mo/yr
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,758 | $35,730 |
$7,509
209,979
kWh
|
$6,249
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $28,761 | $40,319 |
$19,541
506,761
kWh
|
$9,220
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $20,439 | $37,215 |
$11,546
322,787
kWh
|
$8,893
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs