Assessment Year | 2005 |
---|---|
Principal Product | Stainless steel wire |
NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
105,000
ft2
|
Annual Production | 4,800
ton
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $259,612 | 2,853,039 |
kWh
|
$0.091 |
Electricity Demand | $60,626 | 6,277 |
kW-mo/yr
|
$9.66 |
Natural Gas | $119,657 | 16,007 |
MMBtu
|
$7.48 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $87,132 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2425: Use flue gases to heat process or service water | $19,420 | $28,950 | - | - |
$19,420
-
MMBtu
|
- | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $17,581 | $22,500 |
$20,049
220,320
kWh
|
$4,143
-
kW-mo/yr
|
$(-6,611.0)
-
MMBtu
|
- | |
03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $13,916 | $25,000 |
$13,101
143,967
kWh
|
$815
-
kW-mo/yr
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,267 | $160 |
$4,367
47,986
kWh
|
$900
-
kW-mo/yr
|
- | - | |
05 | 2.2514: Cover open tanks | $4,121 | $1,428 | - | - |
$4,121
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,731 | $24,510 |
$12,209
134,163
kWh
|
$2,522
-
kW-mo/yr
|
- | - | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $12,096 | $17,000 | - | - | - |
$12,096
-
lb
|
|
TOTAL RECOMMENDED | $87,132 | $119,548 |
$49,726
546,436
kWh
|
$8,380
-
kW-mo/yr
|
$16,930
-
MMBtu
|
$12,096
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs