| Assessment Year | 2005 |
|---|---|
| Principal Product | Brick and clay potter |
| NAICS | 327120: Clay Building Material and Refractories Manufacturing |
| SIC | 3251: Brick and Structural Clay Tile |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
200,000
ft2
|
| Annual Production | 137,000
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $894,177 | 8,623,031 |
kWh
|
$0.10 |
| Electricity Demand | $308,784 | 23,416 |
kW-mo/yr
|
$13.19 |
| Natural Gas | $291,505 | 513,901 |
MMBtu
|
$0.57 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,898,244 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,308,000 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2314: Replace heat treating oven with more efficient unit | $578,544 | $2,450,000 | - | - |
$578,544
-
MMBtu
|
- | - | |
| 02 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $570,334 | $1,600,000 |
$688,485
6,639,200
kWh
|
$126,624
-
kW-mo/yr
|
$(-244,775.0)
-
MMBtu
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $313,658 | $79,766 |
$267,005
2,574,784
kWh
|
$46,653
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $75,000 | $74,450 |
$75,000
721,000
kWh
|
- | - | - | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $65,420 | $68,600 |
$65,420
630,854
kWh
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,645 | $13,000 |
$11,614
112,000
kWh
|
$2,031
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,076 | $1,300 |
$4,324
41,700
kWh
|
$752
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,012 | $6,000 |
$2,564
24,725
kWh
|
$448
-
kW-mo/yr
|
- | - | - | |
| 09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $11,700 | $18,500 | - | - | - |
$11,700
-
lb
|
- | |
| 10 | 4.445: Install equipment to move product | $261,855 | $40,000 | - | - | - | - | $261,855 | |
| TOTAL RECOMMENDED | $1,898,244 | $4,351,616 |
$1,114,412
10,744,263
kWh
|
$176,508
-
kW-mo/yr
|
$333,769
-
MMBtu
|
$11,700
-
lb
|
$261,855 | ||
| TOTAL IMPLEMENTED | $1,308,000 | $1,883,116 |
$1,114,412
10,744,263
kWh
|
$176,508
-
kW-mo/yr
|
$(-244,775.0)
-
MMBtu
|
- | $261,855 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs